The ICC G16, G17 and F49 Exams for Missouri's Statewide License
Updated 2026-11-06
Missouri's statewide electrical contractor license requires a nationally standardized exam rather than a state-written one. Of the options on the approved list kept by the Office of Statewide Electrical Contractors, the International Code Council exams are the easiest to schedule: you register with Pearson VUE without any pre-authorization from the state.
Three ICC exams on that list use the newest code editions it allows. This guide sets their formats and outlines side by side, from ICC's National Contractor/Trades Examination Information Bulletin published June 30, 2026, and OSEC's approved list, so you can pick one and study to its weights.
Missouri candidates who already passed one of these exams for another board can often use that result instead, as the companion guide explains.
Three exams, two code editions
The approved list fixes the edition for each exam, and Missouri has no statewide electrical code of its own to change it:
- G16 Master Electrician: 100 questions, open book, 5 hours, on the 2017 NEC, with Ugly's Electrical Reference (any edition) also allowed.
- G17 Journeyman Electrician: 80 questions, open book, 4 hours, on the 2017 NEC, with Ugly's also allowed.
- F49 Electrical Contractor: 80 questions, open book, 3 hours 30 minutes, on the 2014 NEC alone.
How to choose
Any of the three satisfies the exam requirement, because 20 CSR 2117-2.020 accepts contractor, master and journeyman level exams. The choice comes down to code edition and stamina. G16 and G17 test the 2017 NEC, while F49 tests the 2014 edition, so pick the edition you know or can borrow. F49 is shorter in clock time but gives you less time per question: about 2.6 minutes, against 3 minutes on both G16 and G17.
The approved list also names F16 and F17, the 2014 NEC versions of the master and journeyman exams, which carry the same weights as G16 and G17. ICC offers newer editions on the 2020 and 2023 NEC, but they do not appear on OSEC's 2022 list. Confirm with OSEC before buying a different exam, since a non-listed exam may not count.
G16 Master Electrician outline
The G16 weights, as printed in ICC's bulletin, put wiring methods, services and branch circuits at the top:
Services, branch circuits and wiring methods together make up 51 percent, or about 51 of the 100 questions. The Services area alone spans service and fault current, service load calculations, service equipment and conductors, transformers, system grounding and bonding, and temporary service wiring, so a master candidate should be able to move from a load calculation to a grounding electrode conductor size without losing the thread.
- Wiring Methods and Materials: 19 percent.
- Services and Service Equipment: 16 percent, and Branch Circuits and Conductors: 16 percent.
- General Knowledge (theory, general load calculations, definitions, plan reading): 12 percent, and Special Occupancies, Equipment and Conditions: 12 percent.
- Equipment and Devices: 10 percent; Motors and Generators: 8 percent.
- Feeders: 4 percent; Control Devices: 3 percent.
G17 Journeyman Electrician outline
G17 uses the same nine content areas and subtopics as G16 but leans harder on installation work. Wiring Methods and Materials is 26 percent, Branch Circuits and Conductors 19 percent, Equipment and Devices 13 percent, and Services and Special Occupancies 11 percent each. General Knowledge and Motors and Generators are 6 percent each, and Feeders and Control Devices 4 percent each.
Raceway fill, box fill, cable support and underground burial depths therefore matter more on G17 than service and load calculations, which carry more weight on G16.
In question counts on an 80-item exam, that is roughly 21 items on wiring methods, 15 on branch circuits and conductors, 10 on equipment and devices and 9 each on services and special occupancies.
F49 Electrical Contractor outline
F49 is organized more like the NEC's own chapters. Branch Circuit and Feeder Calculations and Wiring Methods and Distribution Systems are 19 percent each, Services 17 percent, General Use Equipment 12 percent, General Requirements 10 percent, Special Occupancies 9 percent, and Special Equipment and Special Systems 7 percent each. The bulletin prints no subtopics for F49.
Nearly two questions in five come from calculations and wiring methods, so a candidate who can run a dwelling or commercial load calculation quickly in the 2014 edition is well placed. Several sections were renumbered in later editions, so study from the edition the exam names.
Translated to an 80-question form, the two largest areas are about 15 questions each, Services about 14, General Use Equipment about 10 and General Requirements 8.
Registering and test day
Go to Pearson VUE's ICC page, choose the National Contractor/Trades program for jurisdictions that do not require pre-authorization, create a web account, then select and pay for the exam; ICC's bulletin lists the fee as $120. Questions are four-option multiple choice and results appear immediately. A failed candidate must wait 10 days before retaking.
The bulletin does not print a passing score; ICC shows it in its exam catalog, so check it there when you register. None of the three exams tests Missouri law. Keep your score report, because you submit proof of passing with your OSEC application.
The ICC route is not the only one. Prov's Missouri-listed electrical exams are scheduled at provexam.com with no sponsorship from OSEC, and NASCLA's electrical contractor and journeyman exams are administered by PSI. Whichever vendor you choose, use its own bulletin for references, timing and identification rules.
Practice tied to each outline
ContractorPrepHQ has a 150-question bank for each exam: /missouri/g16-master-electrician and /missouri/g17-journeyman-electrician on the 2017 NEC, and /missouri/f49-electrical-contractor on the 2014 NEC, each split by ICC's content weights and explained question by question. A trade bank costs $149 once. Work the bank in the same edition you will carry into the test center so your tabs and page memory match.
Common questions
- Which ICC exam should I take for the Missouri statewide license?
- Any exam on OSEC's approved list works. G16 (master) and G17 (journeyman) use the 2017 NEC; F49 (contractor) uses the 2014 NEC.
- Are the ICC electrical exams open book?
- Yes. G16, G17 and F49 are all open book. Bring a copy of the NEC edition the exam names, plus Ugly's for G16 or G17 if you want it, and check the bulletin for its rules on tabs and notes.
- Do I need approval from Missouri before scheduling?
- No. OSEC's list says ICC exams are scheduled through Pearson VUE's National Contractor/Trades program, which needs no pre-authorization, and Prov does not require sponsorship either.
- Can I take the 2020 or 2023 NEC version of the ICC exam?
- Those versions are not on OSEC's approved list, which was last revised in February 2022. Ask OSEC at (573) 522-3280 before you buy one.
- What can I bring into the G16 or G17 exam?
- The 2017 NEC and Ugly's Electrical Reference, any edition. For F49 the only listed reference is the 2014 NEC.
- How soon can I retake an ICC exam?
- ICC's bulletin requires a 10-day wait between attempts, and each attempt is paid separately.
Keep reading
Sources
General information, not legal advice. Confirm current requirements, fees and forms with the state licensing board.