How to Get a General Contractor License in Alabama
Updated 2026-09-28
Alabama licenses commercial and heavy construction contractors through the Alabama Licensing Board for General Contractors, based in Montgomery. The law is Chapter 8 of Title 34 of the Code of Alabama. Residential construction and remodeling fall to a different agency, the Home Builders Licensure Board, so a company that builds houses should start there instead.
This guide covers when an Alabama license is required, how the prime and subcontractor applications work, the financial statement that sets your bid limit, the exams, reciprocity and renewal. The board revised the exemptions in Section 34-8-7 through Act 2026-396, effective October 1, 2026, so confirm how the current law applies to your work before you bid.
When you need a license
The board's law page defines a general contractor as one who undertakes to construct or superintend the construction, alteration, maintenance, repair, rehabilitation, remediation, reclamation or demolition of any building, highway, sewer, structure, site work, grading, paving or project in Alabama where the cost, including labor and materials, is $100,000 or more. Swimming pool construction is covered at $5,000 or more.
Subcontractors are covered too. A subcontractor performing a contract of $100,000 or more ($5,000 for pools) under a licensed prime must be licensed. A prime may receive bids from unlicensed subcontractors, but the subcontractor must be licensed before beginning work. When a prime awards a subcontract it becomes an awarding authority, and if an unlicensed sub starts covered work, the prime and the sub are both in violation.
Awarding authorities, architects and engineers must put notice in their bid specifications that a general contractor license is required before a prime can bid. The board also reminds applicants that its license is separate from the state and county privilege license.
Prime contractor application
The prime application costs $300, paid by cashier's check or money order; personal and company checks are returned. It must be on file at least 30 days before a regularly scheduled board meeting, and the board meets quarterly. The instructions list what goes with it:
- Proof of current liability insurance naming the applicant, with the board as certificate holder.
- A dated print screen of the entity's record from the Alabama Secretary of State (not needed for individuals or general partnerships).
- A Qualifying Party Form for each qualifier.
- A current financial statement, no more than one year old.
- A work experience section for each classification requested, with a Principal Individual Questionnaire for anyone whose experience should be counted.
- Three reference forms from licensed general contractors, registered architects, registered engineers or other qualified persons, all for commercial or industrial work in the requested classification.
- An organizational chart.
Financial statements and bid limits
Your financial statement sets your bid limit. The board accepts an audited, reviewed or compiled statement prepared under generally accepted accounting principles by a CPA or a board-approved licensed public accountant; the Alabama Department of Transportation booklet is also accepted. Cash or tax basis statements are not, and deficits are not acceptable. Every applicant needs a minimum net worth and working capital of $10,000.
Two tools can raise a limit once those minimums are met. A line of credit from a state or federally chartered bank or savings association may lift working capital to the level of net worth. A personal or parent company financial statement, backed by a notarized guaranty agreement, may raise the bid limit by one step. Existing licensees use a separate bid limit increase request form.
Subcontractor application
The subcontractor application costs $150 and must be completed in full. It requires three references from general contractors, architects, engineers or awarding authorities you have worked for, with the project location, description, contract amount and date for each. The board's page notes that a subcontractor may bid to a general contractor but cannot start the job until licensed.
Exams
The board's testing page says every application received since January 22, 2008 requires a trade exam as well as the Business and Law exam. PSI Services gives both. The prime instructions call the business exam Alabama Business and Project Management, while the PSI bulletin titles it the Business and Law Examination; it is 50 questions in 120 minutes with a 70 percent passing score.
A complete application must be on file before you can register, and the instructions warn that testing eligibility may not be decided until the board has reviewed it. After you pass, it is your job to send passing scores to the board. The trade exam depends on the classification: the PSI bulletin lists dozens, from building construction, highways and streets and municipal and utility work to roofing and sheet metal, masonry, concrete and elevator work.
Reciprocity
Alabama has reciprocity with Arkansas, Louisiana, Mississippi, North Carolina and Tennessee. The prime instructions name the general contractor boards of Arkansas, Louisiana, Mississippi and Tennessee and the North Carolina State Board of Electrical Contractors. You need a license in good standing held for at least one year in the same classification, and the qualifying party in Alabama must be the same person who qualifies the license in the other state.
Reciprocity waives only the trade portion. The board's reciprocity page states that the business law portion is not waived, and the application must be on file for 30 days with an out-of-state verification form before a license can be issued.
Renewal
Alabama licenses renew each year in a month set by the first letter of the company name, from March for names beginning I through L to December for names beginning with A. The renewal fee is $200 for a prime and $100 for a subcontractor, forms are online only, and renewals sent more than 45 days before expiration may be returned. A license not renewed within a year of expiration requires a new application and both the trade and business and law exams again.
If you are working toward the Business and Law and trade exams, ContractorPrepHQ has Alabama practice built from the PSI outlines and references: original questions, a diagnostic, topic drills with explanations and timed practice exams with a readiness score. Business and Law prep is $99 and trade prep is $149 with Business and Law included, both a one-time price with lifetime access and a 30-day money-back guarantee. It is independent practice and has no role in the board's application review.
Common questions
- At what dollar amount do I need an Alabama general contractor license?
- When the cost of the undertaking, including labor and materials, is $100,000 or more, or $5,000 or more for swimming pools, according to the board's law page. Check the October 2026 exemption changes before relying on an exemption.
- Does the Alabama general contractors board license home builders?
- Residential construction and remodeling are regulated by the separate Alabama Home Builders Licensure Board. The general contractors board handles commercial, industrial and heavy work.
- How much does the Alabama application cost?
- The prime contractor application is $300 and the subcontractor application is $150, per the board's apply page. Exam fees are paid separately to PSI.
- Does reciprocity let me skip the Alabama exams?
- Only the trade exam. The Business and Law exam is never waived, and you need at least a year of licensure in the same classification in a reciprocal state.
Keep reading
Sources
General information, not legal advice. Confirm current requirements, fees and forms with the state licensing board.